Pape-Dawson is providing construction management and inspection services for this program which includes 85 miles of water pipeline spanning across Caldwell, Guadalupe, and Hays Counties.
As the Owner’s Representative for the program, our Construction Management and Inspection team oversees eight separate concurrent construction projects. Pape-Dawson leads this multi-consultant /multi-contractor effort through innovative technical solutions, collaborative stakeholder engagement, and hands-on, problem solving management style.
Highlights:
- $420 million construction value
- Oversight of multiple, concurrent construction packages including:
- Water treatment plant with 3 ground storage tanks
- Booster pump station with a ground storage tank
- 5 water transmission pipeline segments (85 miles)
- 3 elevated storage tanks
- 2 major river crossings
- 8 major road/railroad crossings
- Management of over 250 landowners
- Expert program-level leadership of
- 8 Design consultants
- 5 General contractors
Other Construction Management and Inspection Projects
CoSA Public Works – Construction Inspection Task Order
Pape-Dawson has been providing construction management services for the City of San Antonio Public Works Department, acting as a liaison between contractors and City staff.
Kendall County WCID #3A
Pape-Dawson routinely provides inspection services to independent utility districts across Texas. WCID #3A located in Kendall County is one of those districts which includes 374 acres of mixed-use development.
Vista Ridge Regional Water Supply Project
Pape-Dawson effectively provided Owner’s Representative services in the successful on-time delivery of this 142-mile water pipeline spanning 7 counties, crossing 3 major rivers, and involving over 500 parcels of land.